The question usually arrives after the measuring is done. The car fits, the gate is wide enough, and everybody agrees the platform should go in front of the house. Then the contractor asks whether you want it on top of the ground or in it, and the answers online sound like a matter of taste.
It is not a matter of taste. An above ground car turntable and a recessed pit installation solve the same turning problem with two different sets of groundworks, two different edge details and two different long-term maintenance jobs. Which one is right is decided by what is under the surface and how you want to arrive. Start with the ground you already have, and the rest of the decision follows from it.
What each build is made from · Which build fits your site · Jump to the enquiry form
Both configurations use the same rotating equipment. What changes is the structure under the deck and the way the platform meets the surrounding ground. These are named parts you can ask any supplier to list:
Every line above is a part or a drawing, not an adjective. A supplier who cannot name them is describing a picture, not an installation. Here is how to judge the two builds once you have the parts list in front of you.
Run those five checks and the choice between the two builds stops being a preference and becomes a consequence of the site.
Use an above ground car turntable when the existing surface is sound and you want to keep it: the platform arrives as equipment, the site work is limited to anchoring and the transition at the edge. Choose a recessed pit installation when the deck must sit level with the surrounding finish, and the ground can be opened up, drained and reinstated properly. Neither is the better product on its own; one of them is the better answer for your ground.
That is the whole decision in one sentence, but it leaves the part nobody can settle from a photograph: what the ground is made of, where the water goes and who is responsible for each line of the work. We do not guess that part. The civil foundation drawing and the edge detail are issued with the equipment so your contractor can price the site side before you commit.
If the approach to the platform is steep or drains badly, that is related but separate. Our driveway site checks and garage installation checks cover the arrival routes; a correctly built platform does not remove the need to check the ground that leads to it.
| Site condition | What is checked first | Build that usually follows |
|---|---|---|
| Sound existing hardstanding, level surface | Slab condition, thickness, anchoring and the step at the platform edge | Low-profile surface-mounted frame with a defined transition |
| Finish must be level with the surrounding paving | Excavation depth, drainage fall and the infill material to be carried | Recessed tray, pit-edge angle and client-supplied infill |
| Ground condition not confirmed yet | What lies below the surface and whether an existing drain can be used | Undecided until the site is surveyed - no build should be assumed |
Indicative only. Vehicle load, local ground conditions and the surrounding finish all change the specification.
If you cannot tell which row describes your property, that is the gap worth closing. Send a photo of the ground and the platform location → and our engineers will tell you which build the site can support.
The rest of this page is the detailed installation reference - kept visible for contractors, architects and anyone checking a ground, drainage or control line by line.
| Item | Above-ground / surface-mounted | Recessed pit |
|---|---|---|
| Structural depth | Low-profile frame below the deck, kept shallow within the load rating | Deeper tray and frame set into a prepared excavation |
| Groundworks | Anchoring into the existing hardstanding; cutting and reinstatement only if the surface needs it | Excavation, concrete ring, pit edge and reinstatement of the surrounding finish |
| Drainage | Surface fall checked so water does not stand at the platform edge | Drain point inside the pit and a fall that keeps the tray clear |
| Edge detail | Visible transition between deck and existing surface, specified for vehicles and pedestrians | Edge angle between infill and surrounding paving, set to the finished level |
| Deck finish | Steel plate or aluminium, with a defined edge around the circle | Infill tray for pavers, concrete or stone supplied and laid locally |
| Access after installation | Equipment remains reachable from above and around the frame | Access and service points must be set out before the infill is laid |
| Who does what | Equipment supplier for the platform; local contractor for anchors and surface work | Equipment supplier for the tray and frame; local contractor for excavation, drainage and reinstatement |
Before either build starts, the drawing should answer questions a contractor can actually price. Ask for the foundation and anchor positions, the structural depth under the deck, the transition or edge section at the circle, the location of any drain, and the fixed-to-moving gap around the platform. Where a recessed tray is specified, the infill thickness and the responsibility for laying it should be written down as well. A drawing that only shows the platform outline is not enough to build from.
Installation is not only concrete. Confirm the voltage, frequency and phase for your country, where the control box and wall control sit, and how the remote and emergency stop are specified. Motor protection and the protection of the whole assembly are different things; ask for both by name. If a power cut matters to you, ask what happens when supply returns and whether a manual release or backup option is specified for your configuration - do not assume either is included. These points belong on the same drawing as the edge detail, because the cable route and control position affect the site work.
Yes, where the existing hardstanding is sound and level enough to carry the platform. A surface-mounted build uses a low-profile frame anchored to the prepared surface, with a specified transition at the edge instead of a pit. The contractor still has to check the slab, the anchoring and the fall of water around the circle - no excavation does not mean no site work.
Often, but the slab has to be checked before anyone commits: its condition, thickness, reinforcement and what lies beneath it. We supply the anchor positions and the ground interface detail; your contractor confirms the slab can take the load and the fixing. If it cannot, the drawing has to change before the equipment is ordered, not after it arrives.
With a recessed build, the platform can take a tray infilled with the paving or stone used around it, so the finished surface can match. With a surface-mounted build, the existing paving is kept outside the circle and the deck has a defined edge. Which one preserves more of your paving depends on the layout: send a photo and we will tell you what the edge detail has to do.
Equipment and site work are separate. We supply the platform with a foundation drawing and an edge detail; excavation, concrete, drainage and reinstatement are normally handled by a local contractor, and electrical connection by a local electrician. Ask both parts to be described in writing before you compare offers, so nobody is assuming work that is not in their scope.
Ask three separate questions: what the control does when supply returns, whether the platform can be moved without mains power, and which of those options is specified for your configuration. Motor and control-box protection should be listed separately from the protection of the whole assembly. A waterproof motor alone does not make the installation suitable for standing water - the drain and the edge detail decide that.
Our equipment quotation is EXW, covering the rotating system at the factory. Freight and insurance to your port, import duties and taxes, the groundworks, local electrical connection and installation are quoted separately because they depend on your country and your site. The written, itemised quotation is the only binding figure; a web page cannot price your contractor's work for you.